MAJOR PROJECTS EXECUTED IN THE MENA REGION
The Company’s main activity abroad constitutes Roads, Water and Wastewater, Buildings, and Industrial Projects using Steel Structures, Precast Works, and Tilt-up method of construction.
The Works executed abroad were performed by our sister companies SiteCast General Contracting Company (SCGCC – 100% owned by GCC) in Dubai and Qatar; and Arabian Technical Construction Company (ATCC – 40% owned by GCC) in the Kingdom of Saudi Arabia.




AL KUHAIMI GROUP STORES AND FACTORY - INDUSTRIAL VILLAGE
Location:
Employer:
Description of Work:
Contract Price (USD):
Start & Finish Dates:
Dammam, KSA
Al Kuhaimi Metal Industries Co.
Construction of 9333 m2 –steel structure consisting of 5,000 m2 factory, and the remaining area for Stores. In addition the works include the construction of office Building of 3 storeys of 2400 m2, 40,000 m2 of paved areas and 350 m of Precast Boundary Wall together with all finishing, Electro-Mechanical, overhead cranes and external works for the Project.
$4,500,000
From 15.01.2015 To 31.12.2016




AKOYA PARK - ROCHESTER, BELHAM, TRINITY CLUSTERS
Location:
Employer:
Description of Work:
Contract Price (USD):
Start & Finish Dates:
Dubai, UAE
Gulf Precast Co./DAMAC Crescent Properties Company LLC
Construction of precast skeleton works using Tilt Up method of Construction for TH-M & TH-M1 Types of Four-Villa-Clusters totaling 34 clusters consisting of 68 Villas/TH-M and 68 Villas/TH-M1, and Three-Villa-Clusters totaling 41 clusters consisting of 82 Villas/TH-M and 41 Villas TH-M1.
$5,290,462
From 01.11.2015 To 20.07.2016




AL KHOR ACADEMY
Location:
Employer:
Description of Work:
Contract Price (USD):
Start & Finish Dates:
Al Khor, Qatar
HBK Contracting Co. WLL/Qatar Foundation
The project consisted of nine two story teaching clusters and buildings in addition to an administration building, infrastructure, hard and soft landscape, finishing, and electro-mechanical works. The scope of works included Value Engineering, Structural Re-design, and Construction of all buildings. The Design and Construction of the Skeleton Works using the Tilt-Up method of Construction for the entire built-up area of 56,000 square meter was completed within nine months.
$18,361,690
From 01.06.2015 To 15.03.2016




AL KHOR RECREATION CENTER
Location:
Employer:
Description of Work:
Contract Price (USD):
Start & Finish Dates:
Al Khor, Qatar
HBK Contracting Co. WLL/Qatar Foundation
The scope of works includes Value Engineering, Structural Re-Design for the whole building of a built up area of 12,700 square meter, and Skeleton Construction consisting of structural steel columns and beams for small spans and low roofs with Steel girders for spans of 25 & 30 m loaded on Insulated Tilt Up Load Bearing Walls for the Two Gyms, swimming pools and Cafeteria areas. Corrugated sheets and concrete topping and foam-concrete were used for roofs.
$3,740,960
From 15.08.2016 To 15.12.2016




AL WAKRA ACADEMY
Location:
Employer:
Description of Work:
Contract Price (USD):
Start & Finish Dates:
Al Wakra, Qatar
HBK Contracting Co. WLL/Qatar Foundation
The scope of works includes, Value Engineering, Structural Re-Design for the whole building of a built up area of around 52,500 square meter and Skeleton Construction consisting of the use of insulated tilt walls for the envelope of the buildings, the interior structure consisted of solid tilt-up shear walls, precast columns, steel beams and joists topped by metal sheet decking and concrete topping. Structural steel girders and beams for recreation (spans up to 32m) loaded on Insulated Tilt Up load bearing walls for the two gyms, swimming pools and Cafeteria areas.
Corrugated sheets and concrete topping and foam-concrete were used for roofs.
Duration for the Design-Build of Structure – 10 Months
$12,359,250
From 10.04.2017 To 01.03.2018